Phi Group's Leeds office are on site at Balfour Beatty's Langthwaite Enterprise Zone project in Pontefract. Works are split into the Northern and Southern retaining walls and will be constructed using Phi Group's Andacrib concrete crib retaining wall system.
Northern wall - 193m long with a maximum retained height of 4.80m and face area of 761m2.
Southern wall - 347m long with a maximum retained height of 5.20m and face area of 1,205m2.
Works commenced on site in September and are progressing well.